"PROJ environment variable is too long"

Gary WhiteheadMember for 17 years 6 months
Created
3
1
0
I’m getting the above error whenever I try to run a filter on a particular project.
Anyone come across this before? Any suggestions for fixes?

Many thanks,

G

3 replies

Oldest first
  1. 0
    osama Eltantawy ·
    Dear Gary,

    Make the file location under a shorter path than you have.
    for example put the file under under a certain folder under directory c:\
    Regards
    Osama
  2. 0
    Gary Whitehead ·
    Worked like a charm.

    Many thanks, Osama.
  3. 0
    Noman Ismail ·
    Thanks a lot bro.
    I was also experiencing this problem while scheduling my plan.