Scheduling issue

Shah. HBMember for 17 years 10 months
Created
2
1
0
Hi to all

Option f9
schedules activity on the basis of duaration or resource or both?

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Shahul,
    the result depends on:
    a) the activity type: Task = Duration and activity calendar, Independant = Duration and assigned resources calendars, Meeting = Duration and workperiods where all the assigned resources are working at the same time
    b) is the resource driving or not? Driving = Resource, not driving = Duration
    I hope it helps,
    Alexandre
  2. 0
    Shah. HB ·
    Thanks Mr.Alexandre