Planners,
We already established a Baseline Target with resource and cost loaded and established a cash flow it is already approve by client.
This arabic consultant admised me to changed the actual quantity resource based on actual condition at site but my worry is we already established a baseline cashflow from which quantity is related to cost. Is this possible show in a report or layoutto change the actual quantity with without changing my baseline.
Thanks
Jun
We already established a Baseline Target with resource and cost loaded and established a cash flow it is already approve by client.
This arabic consultant admised me to changed the actual quantity resource based on actual condition at site but my worry is we already established a baseline cashflow from which quantity is related to cost. Is this possible show in a report or layoutto change the actual quantity with without changing my baseline.
Thanks
Jun
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?