Summary or Filter

James bidMember for 17 years
Created
3
1
0
Hi Guys!

If I want to view the summary of certain level.. Example the summary of Level 3 construction. should I go to Format\ Summarize all? or Filter, if in Filter How can I do it?
I tried this thing (format\Summarize all)but still all the levels was shown. I need only the level 3 summary.
thank you and Good day

Chris

3 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi
    you could do for level 3 the same format summarize option but select the respective levels
  2. 0
    James bid ·
    Good day Shahul!

    I cannot get.
    Still Engineering and procurementn showed in the summary. I need only the Construction.

    Can u give me step by step?

    Thank you
  3. 0
    Shah. HB ·
    1.Better you could go for filter option to list out group of construction activities under construction WBS

    2.Have you build your WBS using WBS option or activity codes option?

Log in or join to reply