ho to examine duration of an activity ?

Irfan KhanMember for 17 years 3 months
Created
4
2
0
Hi to all,

i would like to know that how will assign a duration of an activity.

thanks......

4 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi

    you need to find out duration for an activity or you need to know procedure for assigning duration
  2. 0
    Sajid Balma ·
    I believe you wanted to ask how to DETERMINE/ESTABLISH the duration of an activity.

    If this is the case, you need to ask the site management in assessing the duration using their broder knowledge & work experience of execution of such tasks.

    Regards
  3. 0
    Shah. HB ·
    I guess this formula would give you a clue

    Activity duration = work quantity / [ Production rate * Resource usage ]
  4. 0
    Sajid Balma ·
    Hi Shahul
    The formula is excellemt. But, sugges me who is going to define the Production Rate.

    As a planner, I am not supposed to know everything. Engaging site management is not only important to develop a meaningful Programme but a must for the ownership purposes.

    Regards

Log in or join to reply