Is it possible to calculate duration of tasks with P3?

4 replies

Oldest first
  1. 0
    Osama Warid ·
    Yes of course
  2. 0
    Bryc Ali ·
    could you explain me, the method please
  3. 0
    Osama Warid ·
    1- You need to estimate the Qty. for each resource assigned to the activity

    2-Find the average productivity for each

    3- Specify the availability for each resource

    4- Mark the driven resources

    Then the biggest duration will be considered, which is already calculated as a result for the steps 1-4 above
  4. 0
    Shah. HB ·
    hi
    check this formula ,i thrust it would be useful to you

    Driving Resource Duration = Quantity to complete / units per time period