P3 - Activity description width

Shaik YakubMember for 19 years 2 months
Created
4
1
0
Hi,

Is there any option in P3,that we can write more than 48 Charecters in Activity Description column?


Thanks
Shaik

4 replies

Oldest first
  1. 0
    Gary Whitehead ·
    Moved to P3 forum.
  2. 0
    Paul Harris ·
    No that is the limit.


    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
    www.primavera.com.au - a Primavera scheduling software resources site
  3. 0
    Lawrence Cuozzo ·
    The column description with is limited, but if you are putting descriptions on the bars in your chart, you can extend the description length by using the log field and have the start of the log butt up againt the end of the description so it looks like its all one field.

    Lawrence
  4. 0
    Santhosh kumar ·
    Hi Shaik,

    48 characters is a constraint in P3.But you can use "LOG" option and make it visible on the bar chart.