Links in P3.1

Santhosh kumarMember for 18 years
Created
2
1
0
I have Civil,Mechanical,Electrical,Commissioning activites in my schedule.
All these are inter and intra linked.Now i want to delete the inter links and the intra links of electrical activities only and maintain the other inter & intra links of other activities.

Is it possible?

2 replies

Oldest first
  1. 0
    Safak Vural ·
    Dear Santhosh,

    "Store Fragnet" for the activities you want to keep internal relations, then delete the activities from the schedule and use "Retrieve Fragnet" to implant the activity group to the schedule again. You will get rid of the relations from out of the selected group.

    Reagards,

    Safak
  2. 0
    Santhosh kumar ·
    Dear Safak,

    Thanks.That seems to be the only feasible solution.