Showing Client delay in Started activity
In the Open Standard
Olubukola FasoyinMember for 18 years 7 months
- Created
- 3
- 4
0
Hi guys,
Could anyone tell me best way to reflect client’s delay on an activity already started prior to the delay event and started prior to the last accepted baseline.
1. Would it be acceptable to simply add the delay period e.g 12days to the the duration of the concerned activity in the last accepted baseline?
Cheers
Bukki
Could anyone tell me best way to reflect client’s delay on an activity already started prior to the delay event and started prior to the last accepted baseline.
1. Would it be acceptable to simply add the delay period e.g 12days to the the duration of the concerned activity in the last accepted baseline?
Cheers
Bukki
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?