Edit activity description text

Rajesh VarmaMember for 16 years 8 months
Created
6
1
0
Hi,
I would be thankfull if anyone can suggest me a method to edit the text of activity description, so that it automatically gets changed in the whole program,wherever the same description appears. Hope the querry is clear.
Raj

6 replies

Oldest first
  1. 0
    Gary Whitehead ·
    If you want to replace the entire description for a new description, you can use a global change (tools, global change)
    It’s a fairly self explanantory process -you basically set up filter and a new description, and it overwrites the decription for all activities that satisfy the filter.

    There’s a ’trial run’ option I suggest you use to make sure it works as planned before making the change for real.
  2. 0
    Rajesh Varma ·
    Hi Gary,
    Thanks for your response. I tried,but not able to set up a filter for activity description and change tab under global changes will not allow typing a long text,which is my new description.
    Regards,
    Raj
  3. 0
    Gary Whitehead ·
    Another option is to set up a normal filter showing only those activities you want to change, type in the new description in the top activity, use your mouse to highlight all activities in the filter, right click and select ’fill cell’

    You say you’re not able to set up a filter for activity description -why not? what problem are you encountering?
  4. 0
    Rajesh Varma ·
    Hi Gary,
    Yes, that is the best option.
    Thanks,
    Raj
  5. 0
    Santhosh kumar Narayanan ·
    Global change is the right one. There wont be any problem in doing that. Or else try to export to excell

    Tools>Project utilities>Export. Select the required field you want to export and select file type as WK1 or WKS. Complete you all eidit, etc in excell then import back.

  6. 0
    Anbin Ponnith ·
    Hai
    Try to Filter the Activity you want to Change&Organise the activity to a single Level.Edit the activity Description in First Cell
    Select Edit->Fill Down

    Regards
    Anbin Ponnith

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?