Import to Excel

Alberto ClaveronMember for 18 years 1 month
Created
4
2
0

Some activities of my resources has 8 digits number,but when i import it in Excel using Resources-Tabular-Loading and save it in DBF format the figures has been limited to 5 digits.Please help how to correct so i can make my weekly plan & "S" cuve.

Thank you.

4 replies

Oldest first
  1. 0
    Harzelli Bouasria ·
    hi
    open your file with excel and change number of digit with cell format
  2. 0
    Safak Vural ·
    Hi,

    You shall make column width 15(max) and decimal 2(max) at Format Section of your Loading Report Interface in P3.

    Regards,

    Safak VURAL
  3. 0
    Alberto Claveron ·
    Hi Safak & Harzelli,
    I did what you have suggested but when i generate report in P3 a message shows "A Rich Text Format Document is too long.Failed to open Document".If i export it in CSV Format some of the activities which i input million units say 11,031,635.21 becomes 11,031.00.Changing number of digits in cell format in excel doesn’t make a difference too. My schedule has 635 activities and 94 weeks duration.
    Thank you & Regards...
  4. 0
    Safak Vural ·
    Dear Alberto,

    Select export to CSV file and use 2 decimals.

    You may need to change decimal sign of windows . to , or vice versa.

    Regards,

    Safak VURAL