Hi folks,

I have received a PRX file from one of our sub-contractor. After restoring, i unable to open the file i am getting a message " TARGET FILE NOT FOUND".

How do i open this file.

Regards,

Richu

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Richu,
    Click File-> Open then highlight the Project you wanted to open then click Overview. Click Target tab and remove the target project and close. Then Open it again that should work.
  2. 0
    Richu Rose ·
    Rodel,

    Thank you very much.