how P3 summarize resource percent complete

Mimoune DjouallahMember for 20 years
Created
5
1
0

hi dear planners,

how P3 summarize resource percent complete !?

best regards

5 replies

Oldest first
  1. 0
    Craig Brough ·
    Hi

    I have not P3 open right now but here is a starter for 10 (or 2):

    Group & Sort by resource and set the columns to display % complete.

    Or, Export activity data grouped by resource. Export Total budget Quantity, Actual, and remaining and you can derive % Complete from this

    Hope this helps.

    Craig
  2. 0
    Mimoune Djouallah ·
    thanks craig

    what i don’t understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !

    best regards
    Mimoune
  3. 0
    Rodel Marasigan ·
    Mimoune,
    P3 calculate resource percent complete by resource proportion or weightings.
    ex:Act1 have 2 resource with diff resource % complete
    R1 = 40 units * 20% = 8 unit
    R2 = 80 units * 25% = 20 unit
    R/C % complete = (8+20)/(40+80) = 23.33% or 23%
  4. 0
    Harzelli Bouasria ·
    Hi mimoune
    in fact P3 calculate the average of ressources (la moyenne des ressources).

    A+
  5. 0
    Mimoune Djouallah ·
    thanks every body for your reply

    best regards

Log in or join to reply