Skip to content

Weighbridge construction

Rick AquinoMember for 21 years 6 months
Created
6
3
0
Hello Guyz,

Can you please give me a sample of activites regarding construction of a weighbridge with ramp and foundation, and duration for a 3m x 18m.

Thanks,


6 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Rick

    Its just a box in the ground with some kit in it.

    Whats your problem?

    Best regards

    Mike Testro
  2. 0
    Shah Syed Zaheer ·
    Hi I think these may help you.

    Excavation 2 days
    PCC 15 days
    Ramp 10 days
    Installation of mechanical eqpts 10 days
    Electrical installations 7 days
    All in all they shld finish within 40 -45 days
  3. 0
    Mike Testro ·
    Hi Shahab

    You forgot the drainage.

    It will also need a cabin for the operator and the calibration kit.

    Best regards

    Mike Testro
  4. 0
    Shah Syed Zaheer ·
    Hellow Mike
    Yes I was working on them thanks.
    1. Crash Barrier 1 day
    2. Cable routing 2 days
    3. Ramp may require only 5 days.

    Can give u detail tommorrow
  5. 0
    Shah Syed Zaheer ·
    Mike,
    These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so.
  6. 0
    Rick Aquino ·
    Dear Shahab,

    Thank you very much for sharing it,

    Gratitude!

    Rick

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?