Opening P6 file in P3

Jason RowleyMember for 16 years 2 months
Created
2
1
0
Just received an .xer file from a work colleague who is using P6. Unfortunately i am a P3 user. Is there any way of opening P6 File in P3? or does the P6 user have to save to a different file format?

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Jason,
    Ask your colleague to save it to P3 files from P6 source. Alternatively ask your friend to send you XertoP3 converter which is included on P6 installation.
  2. 0
    Jason Rowley ·
    Thanks Rodel, will do just that.