P3 TO P6 Units issue

Minhas ShaikhMember for 19 years 6 months
Created
1
1
0

Hi Planners,

I have trasfered data from SAP to P3 then p3 to p6. I got everything except following:

The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may cause of some setting or its the way. Can you please resolve my issue as soon as you can. Otherwise I will have to re assign manualy. There are more then 7000 activities.

Thanks

Minhas

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Minhas,in P3 you can

    Hello Minhas,

    in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project

    a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6

    if so, you should divide the duration by 8 in P6 by using Global Change

    Alexandre