Units per hour v’s Budgeted Quantity
In the Open Standard
Jonathan WardMember for 19 years 8 months
- Created
- 6
- 4
0
dear all,
i’m just seeking some clarity on a minor issue that i think i have managed to confuse myself on,, when looking at one activity as an example:
Act Desc = Window Cleaner washes window (very basic but humor me please)
when i look at the required Duration (in this example 10 hrs) can i assume that the Budgeted Quantity would be 10?
also,,
if i now add the correct resource i.e 01 = window cleaner, but i chose to add two window cleaners to this task do i then change the Units Per Hour to 2?
i’m just seeking some clarity on a minor issue that i think i have managed to confuse myself on,, when looking at one activity as an example:
Act Desc = Window Cleaner washes window (very basic but humor me please)
when i look at the required Duration (in this example 10 hrs) can i assume that the Budgeted Quantity would be 10?
also,,
if i now add the correct resource i.e 01 = window cleaner, but i chose to add two window cleaners to this task do i then change the Units Per Hour to 2?
6 replies
Oldest firstLog in or join to reply