Converting project planning units
In the Open Standard
Maurice XMember for 19 years 9 months
- Created
- 3
- 1
0
Hello,
In eed to change a planning setup in hours to a planning in days.
I’ve created a copy with planning unit days and tried to convert the TF and FF Values using export -> divide values by 8 and import, but the FF will not change.
Any suggestions what I can do to convert this project?
Thanks,
Maurice
In eed to change a planning setup in hours to a planning in days.
I’ve created a copy with planning unit days and tried to convert the TF and FF Values using export -> divide values by 8 and import, but the FF will not change.
Any suggestions what I can do to convert this project?
Thanks,
Maurice