Relationships Help required
In the Open Standard
Thomas NicholsonMember for 20 years
- Created
- 1
- 1
0
Hi there,
I wonder if someone could remind me how I could sort this out?
I have 5 activities A, B, C, D & E starting at different times from now until April, I have them all linked into another activity (F)which I need to start with the earliest date of the preceeding activities. However the dates (A-E) start could change and I want activity (F) to reflect the earliest start of them all as and when. I've tried linking them via SS and FS and FF but none make (F) start date equal the earliest date of A-E.
Any ideas?
thanks all.
Thom
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?