Is there resource calander in P3????

Jehad Aldaoud PMP, PMI-SPMember for 16 years
Created
5
1
0

Good morning planners 

is there resources calander in P3 ???

please advise 

best regards 

jihad aldaoud 

5 replies

Oldest first
  1. 0
    Shah. HB ·

    Hi  jiahd aldaoudDefault

    Hi  jiahd aldaoud

    Default resource calendar is unavailable in P3,you can create a calendar in which resource availability is identified and that calendar is assigned to each resources 

  2. 0
    Rafael Davila ·

    Yes you can use resource

    Yes you can use resource calendars in P3, somewhat limited though.

    From: http://download.oracle.com/docs/cd/E20557_01/documentation/P3/P330ref.pdf

    "Use resource calendars to accurately reflect the work schedules of
    your resources: personnel vacations and holidays, equipment
    delivery or lease dates, expected arrival dates, and so forth. P3 only
    uses resource calendars to schedule independent and meeting
    activities. When you define calendars for resources and assign
    those resources to activities, be sure the resources are driving and
    the activity type is independent or meeting."

  3. 0
    Jehad Aldaoud PMP, PMI-SP ·

    many many thanks

    many many thanks 

  4. 0
    Alexandre Faulx-Briole ·

    Hello,it's not 100% true: in

    Hello,

    it's not 100% true: in P3 each and every resource gets automatically its own calendar; create a new resource and then go to Data, Calendars, Resources and you will see this new resource specific calendar;

    in the Data, Resources dialog, the "Base" column displays the "Base" calendar P3 is using as a template for this specific resource's calendar

    In P6 on the other hand, resources do not get a calendar when you create them; you will have to create resource calendars and assign them to resources if needed.

    Alexandre

  5. 0
    Rafael Davila ·

    Alexandre, Maybe you can help

    Alexandre,

    Maybe you can help me remember how P3 and P6 deal with the following simple scenario that combines independent resources with meeting resources.

    Resources A, B and C can work independently of each other but only when D is available, all within Activity 1 calendar.

    There is only one of each resource A, B, C and D and all work on the same shift, from 8 to 5.

     

    Sunday

    Monday

    Tuesday

    Wednesday

    Thursday

    Friday

    Saturday

    Resource A

     

    available

    available

    available

    available

     

     

    Resource B

     

     

    available

    available

    available

    available

     

    Resource C

     

    available

    available

     

    available

    available

     

    Resource D

    available

     

    available

    available

     

    available

    available

    Activity 1

     

    available

    available

    available

     

    available

     

    Activity 1 will be scheduled to work on Tuesday, Wednesday and Friday, three days a week, but not all resources will be working on the same day.

    The following is how I model it now.

    Meet and Indep Resources

    How P3 and P6 handle this 2 activities, 4 resources one shift job?

    Best Regards,

    Rafael