Old lesson in P3 resource graph needed
- Created
- 0
- 2
Hello
I've not posted on here in years. I have recently reverted to using P3 again after a long spell of using P6.
I am using a resourced schedule which has the resource on the cost, the cost also has a price per unit entered onto each resource.
Giving that the price is really man hours and the price per unit is going to be hours per day I should then be able to assume each resource can only work 8 hours per day so if i exceed 8 hours the resource (price per unit column) would show number of men.
So when i do a report - graphics report on resource & Cost I would add in the parameters of what i want to show in the report/chart.
This part is all fine except for one setting: When choosing the content, P3 gives me the choice to divide by a number.
Does this represent 8 hours a day or how many days in a week? I am running the reports per week so I can see man power over the project per week.
Should i use this content setting and divide by 8 to get the correct man power (based on 8 hours a day).
or should it be by 7 to divide by 7 days in a week.
The outcome is obviously different............help
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?