baseline vs as built

Jack ScottMember for 11 years 3 months
Created
2
1
0

A while back, I was working on a claim.  Using P3, I superimposed the as built schedule onto the baseline schedule.  Unfortunately, I can't remember how I did it.  Any help?  Also, does Suretrak have this function?

Thanks!

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi JackThis is how I would do

    Hi Jack

    This is how I would do it.

    Open the original programme.

    Change the durations to the as built dates.

    DO NOT SAVE IT.

    Create an undelying baseline.

    Close the file and DO NOT SAVE It.

    Open the file and you have the as built underlying the as planned.

    Best regards

    Mike Testro

  2. 0
    Zoltan Palffy ·

    how you do it in p3 is

    how you do it in p3 is to

    openthe project

    go to tools

    select project utilities

    select targets this is where you would select the baseline 

    then select forrnat bars 

    select modify in the drop donw by where it says structure

    for the start point select target 1 early or late start

    for the end point select target 1 early or late finish 

    upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar 