Updated ImportExport Utility for P5

David SmithMember for 19 years 3 months
Created
4
38
0
Hi All,
I have a Excel utility that I had sent to me from Primavera Support while I was at the Primavera conference. It said in the email that the tool has not been updated for P5. Has anyone updated this utility for P5? If you have one can I get a copy of it? If not does anyone know what needs to be updated?

I would be grateful for any help or direction on this. I am willing to open the hood on this thing if necessary.

This is what the utility can do:

Activity.xls is designed to facilitate Import and Export of the following:
Activity Details (General Activity Information)
Activity Relationships (Predecessors and Successors)
Activity Code Assignments
Resource Assignments
Activity Steps
Activity Expenses
Activity UDF (User Defined Fields)
Resource Assignment UDF (User Defined Fields)
Activity Step UDF (User Defined Fields)

Thanks In Advance
David

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    David,

    The RA excel utility Activity.xls is mean for P3x only. P5 use SDK API which is included on your P5 installation CD. You can use xls import/export function in P5 which doing the same thing but limited function.

    HTH,
    Rodel
  2. 0
    Sandy Matheson ·
    P5 has export/import facility to/from .xls files but it is fairly laborious with each step to be completed each time. But it works.
  3. 0
    Hemanth Kumar ·
    Install SDK ( If not Installed )
    Explore P5
    You Have 2 Excel Templates

    Cheers
  4. 0
    K D ·
    Hi,
    you can go to POINT and search for prim4617.

    Thanks

Log in or join to reply