Activity codes and the export facility

Kevin MatthewsMember for 20 years 5 months
Created
1
18
0
G’day,

We are finding that after exporting projects in P5 activity codes do not come across. These are Enterprise codes. Is it worth chaning the codes to global and/or project before exporting ?

Keep Planning..

Kevin.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Kevin
    I had the same problem in P6. First I created the EPS-Activity Code. Then during the export the code’s values were created automatically and the activities remained properly assigned. This should work in P5 as well. (Thanks to the German hotline!)

    Hope this works
    Dieter