Open Schedule File Made by P6.1 With P6

Abeer MahmoudMember for 18 years 4 months
Created
6
7
0
Please advise, can I open schedule file made by P6.1 with P6?

If the answer is I can’t please tell me how I open it.



Regards,
Abeer

6 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Abeer

    XER is a text file. Open a copy with editor or notepad. In the first line is "6.1.0" modify into "6.0.0".

    Should work.

    Regards
    Dieter
  2. 0
    Ronald Romero ·
    Hi Abeer,

    Open your file with a text editor like notepad and change the version from 6.1.0 to ERMHDR 6.0.0

    Cheers,

    Ronnie
  3. 0
    Ronald Romero ·
    Hi Abeer,

    Open your file with a text editor like notepad and change the version from 6.1.0 to 6.0.0

    Cheers,

    Ronnie
  4. 0
    Abeer Mahmoud ·



    Thanks Ronald you can’t imagine the happiness you cased to me I appreciate your help very much I was in vacation last month I worked on laptop and I can’t access to planning site to thank you for your great help.

    Thanks again
    Abeer
  5. 0
    Richu Rose ·
    Ronald & Dieter,

    Thank you very much.
    I was struggling to open a P6 6.2.1 xer file in 6.0. Based on the information provided by you guys, i was able to open the file.

    Regards,
    Richu
  6. 0
    Abeer Mahmoud ·
    Dear Dieter thank you very much for your quick response and fast action you solved a big problem I appreciate your help very much sorry for delay I was in vacation last month I worked on laptop and I can’t access to planning site.
    Thanks again
    Abeer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?