Copy a WBS from EPS to Another EPS

Gobinath NarayanasamyMember for 17 years 8 months
Created
1
16
0

HI Friends

How to copy a WBS from one EPS project to another EPS project.

and i want know that possible to view all project(whatever in the database) in WBS layout mode.

1 reply

Oldest first
  1. 0
    Anbin Ponnith ·

    Hi 1.Just Select The Two

    Hi

    1.Just Select The Two Project you want to open (Ctrl Key).

    2. Right Click & Open the Project

    3.Now Both Project Are Opened. You can Collapse it to Level 1 (You can see both project Title) .

    4.Now Click on WBS Window

    5. Just Copy the WBS you Want & Paste the Wbs Where you Want.

    Regards

    Anbin