Skip to content

Slippage Calculation using Total Float

Jeff LimpinMember for 19 years
Created
5
6
0
Guys,

In P3 3.1 is that possible to calculate the current total minus the target total float and put the answer in the column. The reason I’m using this option because if I use the varaiance target finish only give me the change of duration comparison not the slippage impact of the project.

Regards,
jeff

5 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    I broke my head over it but could not do it through global change.

    There is a more crude method of exporting the Target Float and Current Float and importing the difference in a Cutom data column.


    Regards,

    Ashraf
  2. 0
    Larry Rino ·
    Is it really necessary to show the difference (current total float minus the target total float) in P3, if not I suggest to export your P3 data in Ms Excel and put formula in the difference column (present it in Ms Excel).

    I hope these helps.
  3. 0
    Scott Sando ·
    How about:

    Copy the target float figures into a custom field, then create a second custom field subtracting current float from the figure in the first custom field?
  4. 0
    Ashraf Jahangeer ·
    Hi There,

    The question is how to copy?

    Global change is not possible.

    Regards,

    Ashraf
  5. 0
    Ashok Kamath ·
    Can you not establish your Target Project in the Project Overview dialog box (Targets tab)and have a column in your graphical view that shows Variance Target - Early Finish

    Have your Baseline schedule as the first Target Variance column to compare with current.

    This should show you a running tally for slippage.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?