Heloo Friends Long time I havent seeen you.
Please I have qustetion regarding to the manpower sufficieny..If you have project 6 month time, how can I estimate the adequate number of manpwer to finish project on time.?

Your early reply it will help much.
Thank you

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    yes Salah, it’s been a long time, I supposed you’re using P3, or is it P6 now?

    you need to apply quantity surveying on this, for example: if you are dealing with steel works or structural steel fabrication, you need to calculate the total tonnage; number of joints (welded); fitting works; etc. then you can calculate your crew and relate it to your timeframe

    regards
  2. 0
    Samer Zawaydeh ·
    Dear Salah,
    Once you have finished the activity list, the best thing is to site down with the Project Team (Engineer, Managers, Foremen) and discuss the activities and how much manpower they have and how much time they have to complete each activity. It is totally dependent on the project you have. Also, you can take notes of previously completed similar projects.

    Best Regards,

    Samer
  3. 0
    Smiling Shagger ·
    namaste!
    normally Sir, i do like this
    say,
    project milestone=6 months
    say mobilisation =2 weeks
    testing+clearance i.e project close-out= 1 momth
    so, peak resource utilisation = 4.5 months

    extract
    fr construction drwgs= MTO or quantities
    which reflects each trade
    fr productivity rate (maybe from previous job/location)

    at the same time
    construct the cpm schedule
    construct a planning sheet (which a tabulation manner consist of activities /method /ways that we planned to construct the project at site + quantity + productivity rate (reasonable productivity rate for each volume per day or per hour) + resources (manpower/machineries/gangs or team) + planned duration (resonable duration to complete the task/activity). these i normally seat down with various site team/discipline who have vast site experience, just to came up with more realistic reasonable duration.

    then
    i put in all the above resources/duration in cpm schedule, placed targeted completion date and run the schedule.
    normally, it would gives many positve float or many negative floats, in such cases, the adjustment have to be made in duration and resources. once we get the complete cpm, then we construct whatever client want - s curve, resource histogram/loading, driving loading/material graph.

    The above process normally take 1 week or less also depends on team exposure n experience and teamwork.

    Hornylly,
    smilingshagger