Total Manpower

Ronron MartinezMember for 16 years 10 months
Created
2
2
0

Dear All,

, I got a project that will complete within 2-1/2 yrs with estimted manhour of 175,000 Hours, I drafted a schedule that loaded with manpower. Expert advise how much direct workers required to complete the work activity. Thanks a lot.

Regards

Ron

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    if you have the estimated

    if you have the estimated manhours then you should know out of the 175,000 manhours how much is direct and indirect how did you come uo with this numebr in the first place ?

  2. 0
    Vladimir Liberzon ·

    As was discussed before

    As was discussed before resource hours and resource quantities are not proportional.

    But in any case the number of workers is not the same during the project life cycle. The number of workers at any time is determined by the project schedule.