start, finish and total float float

Md Sakib IslamMember for 11 years 1 month
Created
2
8
0

Greetings to All.

(it might be a stupid question)

In P6 project layout we use start, finish and total float columns. we have original duration too. My question is on what basis total float is calculated. because total float = late start- Early start or late start - early start

and we dont enter any kind of early or late start or finsh shedule, but still total float is provided. how is it possible. 

(Thanks in Advance)

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi MDLatest start is where

    Hi MD

    Latest start is where all the float is used up.

    Best regards

    Mike T.

  2. 0
    Rafael Davila ·

    You enter project start,

    You enter project start, activity durations and logic, after schedule run early and late dates are calculated during forward and backward calculations then float values are calculated and all can be shown on the same table.

    • http://www.slideshare.net/AdamGarnham/no-nonsense-guide-to-the-critical-path-and-critical-path-analysis

Log in or join to reply