Planner vs. Scheduler

Ali FarhatMember for 17 years 11 months
Created
7
4
0
I know this might seem trivial, but i would like your opinion regarding the difference between the title "Project Planner" and "Project Scheduler"

7 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Ali,

    It depends on the size of the Project.

    The Planning Job can be done by a person called a "Planner" and the maintenance, updating, or keeping the schedule current, by a person called a "Scheduler".

    Plenty of articles are available online, you need only to run a simple search.

    Best Regards,

    Samer
  2. 0
    Ali Farhat ·
    Thanks Samer,
    I just need to know briefly the job description of both titles.
    I thought a planner PLANS for the activities and sequence while a schedule applies someone’s plan onto a planning tool. Am I right?
  3. 0
    Ali Farhat ·
    I will make myself clearer,
    I once thought that a planner makes the logic of the plan while a scheduler applies somebody’s else logic. i.e. the scheduler is just a tool operator.
  4. 0
    Samer Zawaydeh ·
    Dear Ali,

    The planning process is a team effort. The team should sit and discuss all the deliverables as per Contract and the activities that are required to complete the job.

    The person working throughout the planning process is the Planner, and the output of the Planning Process is the Schedule. The person maintaining the schedule up to the close out of the contract is the Scheduler.

    Smaller projects have one person doing the complete job, while on larger projects you will have many people each working on a certain discipline.

    The choice of title for the Job is up to you.

    Best Regards,

    Samer
  5. 0
    Ali Farhat ·
    Many thanks Samer, I think I am geting the picture
    So far I have been working solo as a free lancer and none of the projects i did exceeded 15M $.
  6. 0
    A D ·
    Here’s the link,

    http://www.planningengineers.org/publications/papers_download.aspx?id=5

    Cheers,
  7. 0
    Ali Farhat ·
    Many thanks Raviraj
    this paper is definitely of great help