How to tell a Builder from a Planner
- Created
- 10
- 2
10 replies
Oldest first- 0MTMike Testro ·
Hi Anoon Of course you would
Hi Anoon
Of course you would know the answer but there are hundreds of planners out there who do not understand such basic fundamentals.
There is another situation where formwork and rebar take a different sequence.
I know you can tell me Anoon but lets see if there are any others.
Best regards
Mike Testro
- 0VAVijay Anbumani ·
Hi Mike, I was working
Hi Mike,
I was working in Building construction firm for 4+ yrs and 2+ yrs in IT park construction now presently iam working as Planning engg at Oman in a firm. Regarding Rebar cutting & Bending will start first and on site Shuttering work will be started first.
I am looking for a Oppening in Planning engg at India, if anybody can help me to get an oppurtunity please revert me back.
Thanks to Planners,
Yur,
J. Vijay
(+96899228423)
- 0MTMike Testro ·
Hi Vijay You are right of
Hi Vijay
You are right of course but in modern construction rebar cutting and bending is done off site and delivered prefabricated.
Its place in the programme is in the lead in items.
My own experience in India is with Punj Lloyd in Gurgaon - they may be looking for planners both in India or maybe Myanmar where they have just started a massive pipeline.
Best regards
Mike Testro
- 0ASAmar Soogrim ·
This is a typical "chicken or
This is a typical "chicken or egg" situation. It all depends on the nature of the activity. Ideally prefabrication of the reinforcement can commence along with prefabrication of the formwork depending on the form system to be used.
The placement of the reinforcement and formwork also is based on the nature on the activity. Where in some cases the following applies
1. Reinforcement then forms
2. Forms then reinforcement
3. % Forms then reinforcement then balance of forms
4. % reinforcement and forms together but reinforcement complete before last forms are placed.
Construction experience will resolve the selection of the option to be applied
Hope this gives some guide to the question
Amar
- 0KTKieran Thomson ·
Hi Mike,Bloody good question
Hi Mike,
Bloody good question sir. My own experience has seen both methods adopted. Another way of asking your quesion is which task finishes first? I don't think there is a right or wrong answer on this as pre-pour checks will dictate the outcome. Truth be told, the pour date is the critical point in all this.
Regards
Kieran
Log in or join to reply