Skip to content

Importing 3 Point Estimates into Pertmaster

Dave JonesMember for 17 years 1 month
Created
0
2
0
I am using the latest versions of P6 and Primavera Risk Analysis 8.6 (formerly Pertmaster).

For each resource assignment, I have a 3 point estimate for the effort .. ie min 6 hrs, likely 12 hrs, max 23 hrs.

There are multiple resource assignments per activity.

How cam I import this data into Pertmaster?

The standard Primavera/Pertmaster integration only allows either:
a) resources to be imported (but no 3 point estimates), or
b) summarised costs with 3 point estimates at the activity level.

Could a Macro importing from an excel file be a possibility? Or are there any other options?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?