Upgrade from Pertmaster (Primavera Risk Analysis) 8.53 to 8.7.1. What is lost?
In the Open Standard
Dennis HanksMember for 19 years 6 months
- Created
- 2
- 1
0
Just upgraded from 8.53 to 8.7.1 and tried to install the Capex module and Cost Loading modules - no joy. The Risk Factors module seems to be pre-installed. I cannot say that I ever used either of the modules, but curious if anyone else has and if they are located elsewhere.
Also, I cannot find any help references to 'conditional branching'. I am almost positive that the feature was available in 8.53 (pretty sure it was part of a tutorial). Where is it now?
Any thoughts appreciated, thanks.