Primavera P6 Critical Analysis
In the Open Standard
Rhys ParryMember for 15 years 1 month
- Created
- 6
- 6
0
Hello
I have a plan in P6 version 2 and after updating activity % and my Expense % Complete to match then schdulling it the end date for the enture project plan went from for example 12 october to 12 november.
I don't know why this has slipped so much as I was thinking it could be to do with some of the Level of Effort activities I have.
Any Ideas guys (can I do a timeline of events to see why the dates have changed so much)
Thanks
6 replies
Oldest firstLog in or join to reply