Armando;
If I understand your question, you are asking if it makes sense to model equipment setting (construction) with incomplete P&IDs? Without knowing your logic or what stage of development the P&Is are, a definative answer is not likely. That said, the primary drivers to equipment setting are equipment delivery and foundations. Equipment purchase requires only the material requistion that often preceeds P&Is but follows block/process flow diagrams. The foundations are another thing, they almost always follow P&I "Issue for Approval". If I was forced to model construction this early in the game (before the Construction Estimate, I assume) and I knew my expected delivery dates, I think it could be done, you would just have to extend your uncertainty range to account for insufficient design.
Short answer: Yes, it can be done, you just will have more uncertainty now than later. Personally, I would not model beyond the level of my current estimate. I would insist that all activities be 'tied-off' - no open ends, before attempting this exercise. If you can't, then it is probably too soon for this level of detail. "No estimate, no schedule. No well crafted schedule/plan, no risk analysis". I think it is too early.
Note: 'All' current scheduling is PDM (precedence diagraming method). ADM 'died' years ago with the widespread usage of computers.