XER WBS import errors
- Created
- 1
- 2
Has anyone encountered errors when importing a WBS IDs into Primaverea Risk Analysis (PRA). What should read
C512-R45/P2.0.010-001.2 (P6)
is reading
C512-R45/P2.0.010-001.0280 (PRA)
It is as if PRA is ignoring the data in the XER file and just auto-incrementing the last 4 numbers as "0280" does not exist in the XER file - I have checked in Notepad. The correct data is also available in the XER it is just that PRA is not using it.
Levels 1 and 2 import correctly - it is 3 onwards that it just whimsically assigns WBS IDs to. Any ideas?
I have tried getting the planner to export v6 and v7 XERs. There are no user fields with the correct ID in either.
All the task IDs import correctly.