Skip to content

Import problem Primavera Risk Analysis mpp file

Martijn VerwoerdMember for 8 years
Created
5
4
0

When I import an MS project file, the duration of the activities are divided by 3.

For example an actitivity has in MS Project a duration of 20 days and after import in PRA only 7 days.

I tried to change the import parameters and match the number of hours per day, but nothing changed.

Anyone familiar with this problem?

5 replies

Oldest first
  1. 0
    Trevor Rabey ·

    Martijn, without seeng it,

    Martijn, without seeng it, hard to say. If you want a quick answer to this, send me the MSP file and I will run the xml import to my P6. my address: trevorATperfect projectDOTcomDOTau

  2. 0
    Martijn Verwoerd ·

    Thanks for the suggestion,

    Thanks for the suggestion, but the problem seem to be solved.

    It has to do with the language settings in MS Project. This need to be in English and not in Dutch (in my case).

  3. 0
    Tom Boyle ·

    Martijn,Thanks very much for

    Martijn,

    Thanks very much for sharing the solution!  Microsoft's proliferation of language packs has complicated a lot of things, and I would not expect PRA (rather long in the tooth) to have easily handled the complications.  Just to clarify, what was the format of the MSP file you were attempting to import?  mpp? (what year?) mpx? xml? (what year?)

    tom

  4. 0
    Martijn Verwoerd ·

    Tom, I tried to import an mpp

    Tom, 

    I tried to import an mpp from Project 2013.

    Regards,

    Martijn

  5. 0
    Tom Boyle ·

    Thanks!

    Thanks!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?