Skip to content

Need Guidance on Schedule Risk analysis

Ibrahim AliyuMember for 10 years 2 months
Created
3
3
0

I have an updated schedule,

3. some activites are completed.

2. some have started but not completed

3. some not yet started.

I want to run a schedule risk analysis to no my probabilistic completion date. the schedule is not resource loaded.

 

whats the best approach to this

3 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Schedule Risk Analysis only

    Schedule Risk Analysis only ever uses remaining durations - there is no risk on completed tasks.

    Couple of websites that contain a lot of good info:

    https://www.riskinteg.com/ and http://www.projectrisk.com/

  2. 0
    Rafael Davila ·

    Please be reminded that each

    Please be reminded that each iteration must be resource-leveled if some resource(s) is (are) limited.  In real life most schedules are resource constrained.  Closing your eyes to the issue of resource usage and availability is not a good idea.

    Project Schedule Risk Analysis Simplified

    Page 8 - If several activities using the same resource are potentially scheduled at the same time, they may require more of that resource than is available. Resource leveling in CPM pushes one or another resource-using activity out in time so that a resource’s usage does not exceed its availability in any time period.  Because each solution in a risk analysis must at least be feasible, it should not violate any resource limitations that exist.  Each iteration must be resource-leveled if some resource(s) is (are) limited.

  3. 0
    Alex Lyaschenko ·

    Hi Ibrahim,It is importnat

    Hi Ibrahim,

    It is importnat which schedudling tool you are going to use. Spider Project would able to produce probability of success (schedule, cost or both) but you would need to have risk data in your schedule.  

    Risk data could be presented a number of ways. Two the most traditional:

    1. Risk to activity durations;  

    2. Risk event. 

    In P6 and MSP you would need to use external plugins but they only support Monter Carlo analsyis. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?