Skip to content

Strict link

Daniel MoraisMember for 8 years 5 months
Created
11
2
0

Hi Everyone,

In my project i have some activities that can't be executed with delay, the second activity is modeled imediatly after first activity. For this reason I set "strict" on this activities.

After scheduling, the report below show me this infortmations. 

Why this happened? Why this happened with this activies and others not happened?

Best Regards,

Daniel Morais

 

 

11 replies

Oldest first
  1. 0
    Daniel Morais ·

    Follow the

    Follow the file...

    https://we.tl/t-hOPkxZopT4

    Password 9999

  2. 0
    Bogdan Leonte ·

    Hello Daniel,When you have

    Hello Daniel,

    When you have multiple successor for an activity you cannot have strict links. If you uncheck Use in scheduling property of link between 0108 and 4335 the strict link will be respected. For all other activities it must be a similar problem (I did not check them all).

    Also you cannot have multiple successor with strict links.

    Vladimir can better explain why the strict link is not respected if an activity has multiple successors.

    Best regards,
    Bogdan

  3. 0
    Rafael Davila ·

    The label Strict Links is

    The label Strict Links is misleading.

  4. 0
    Daniel Morais ·

    Hi Bogdan,Perfectly

    Hi Bogdan,

    Perfectly understood , thank you very much.

    Daniel Morais

  5. 0
    Daniel Morais ·

    Hi Rafael,Why is misleading

    Hi Rafael,

    Why is misleading ?

    Daniel Morais

  6. 0
    Vladimir Liberzon ·

    There are many cases when

    There are many cases when strict links contradict to other conditions and yes, Spider does not always respect strict links.

    We introduced them because there were customer requirements and these customers were happy because they work properly in their projects. When we found that this link property does not work for some cases we decided to eliminate it. But when we had done this many customers requested to keep it despite the problems that appear in some cases. They know that sometimes strictness will not work but still they use them and in most cases it is helpful.

    So we know about the problem with the strict links but keep this feature for our customers.

  7. 0
    Bogdan Leonte ·

    They are indeed useful, you

    They are indeed useful, you only need to know how and when to use them.

  8. 0
    Marcus Possi ·

    Indeed Even if they do not

    Indeed 

    Even if they do not work for some cases, please do not eliminate them. They work for some strict sequence conditions, and they mut not be use without a "permanent medical assistance"   :))

    Bogdan Leonte is right - you must check if they were considered at each schedulling. Trere are also warnings reports about that, if they are not considered.

     

    Imagine three activities with a hard and rigid logict hat cannot be separated from each other- they should be modelled as a planning package instead of a fragnet. There will be no need og strict link or ultra hard modification in programing algorithms.  :)

     

  9. 0
    Marcus Possi ·

    Hey, I haven't tested it

    Hey,
     
    I haven't tested it before, but we should think about complex and high-level features, which only "spider design" and "few planners" can even understand :)
     
     
     
    Could you share SPRJ files (opt-everage-pers)?
     
     
     
    tks
  10. 0
    Rafael Davila ·

    Do Monte Carlo know when not

    Do Monte Carlo know when not to use them and issue the warning? In some iterations there might be respected while in other they might not.

    In the following figure strict deterministic lags are feasible but not optimistic or pesimistic, the probabilistic strict link contradict to other conditions.

    2021-04-11-16-41-03

  11. 0
    Rafael Davila ·

    Why Spider cannot figure it

    Why Spider cannot figure it out if strict links are not mutually exclusive and there are feasible solutions.

    2021-04-12-14-06-51

    2021-04-12-14-16-08

    Among many the following is a feasible solution.  Just delay start of activity 3.

    2021-04-12-14-08-04

    https://www.mediafire.com/file/1mc12f7fo3vxwte/Activities-22.003.sprj/file

    https://www.mediafire.com/file/td9ac94dqhgorva/Activities-22.004.sprj/file

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?