Hello all,
We have had some repeated requests to setup a forum area specially for those avid TILOS fans. So here it is.
TILOS is time-location planning software (also known as time-chainage software) that helps planning engineers in construction and civil engineering industries plan and manage linear construction projects such as road, rail, bridge, pipeline, power cabling, canal and tunnelling projects.
TILOS visually displays project plans in terms of both time and distance so planners can clearly see, for example, the status of a road build project in terms of what needs to be done on each section of the road and by when.
TILOS is the only system that combines the features of a drawing program and a project management system (including scheduling, resource and cost management). TILOS can exchange data with other scheduling systems including Microsoft Project, Primavera/P3, Excel and Asta Powerproject.
TILOS is a windows application that is installed on each PC. It is available as standalone and network version. For the network version, a licence is installed on a server to enable concurrent licencing.
We have had some repeated requests to setup a forum area specially for those avid TILOS fans. So here it is.
TILOS is time-location planning software (also known as time-chainage software) that helps planning engineers in construction and civil engineering industries plan and manage linear construction projects such as road, rail, bridge, pipeline, power cabling, canal and tunnelling projects.
TILOS visually displays project plans in terms of both time and distance so planners can clearly see, for example, the status of a road build project in terms of what needs to be done on each section of the road and by when.
TILOS is the only system that combines the features of a drawing program and a project management system (including scheduling, resource and cost management). TILOS can exchange data with other scheduling systems including Microsoft Project, Primavera/P3, Excel and Asta Powerproject.
TILOS is a windows application that is installed on each PC. It is available as standalone and network version. For the network version, a licence is installed on a server to enable concurrent licencing.
87 replies
Oldest first- 0PJPhilip Jonker ·Hi Guys,
I use Tilos, and it should be of great interest to people who work on linear projects. A bit of discussion would be interesting, and would help to clear peoples minds on Time vs chainage, or line of balance. I am no way associated with the product, but have used it successfully. It can be interfaced with most planning packages, and as such is a handy add-on. - 0AFAndrew Flowerdew ·Richard,
Sorry, don’t quite stretch back to the sixties workwise but I can remember doing it just as you say - A0 drawing board, set square and a long metal ruler always came in handy!
The only difference today is you can resource load the programme, cost it, etc and the software will give you useful answers at the click of a button. The ideas or methods are the same but some of the answers just come quicker! Oh, and the ink doesn’t smudge. - 0AFAndrew Flowerdew ·Richard,
Somehow we managed in days long gone by walking out on site, having a look, marking up a piece of paper on the wall and making decisions - it was the best we could do at the time and it worked, but in those days we seem to have had time to do what we needed to do - and somewhat larger profit margins than we work on today. Then came the recession in the early nineties, profit margins dissapeared (to negative numbers in some cases) and the world got that much tougher. I’ve never seen a job priced since with a profit margin of 20 - 25% as may have been the case pre recession times. We had big enough margins then to make up for the inefficiencies, the cock up’s, the work done twice, the non productive Friday afternoons down the pub.... ....the good old days are long gone.
These days every client wants to have his project finished yesterday, the contractors still want to make their margin or more and if abit of software can take some of the guess work out of the decision making and do it at the click of a buttom then I’m afraid I’m all for it - anything that helps. Phillips quite right though, never take blindly the information that a computer tells you, gut feeling and experience still plays a part in the decision making process, but as I said, if it can help save some time scribbling on paper and pushing buttons on a calculator, then I’m all for it. - 0HDHannes de Bruyne ·Hello Guys,
I know these discussions of the good old days to well. I have to listen to those stories on sites, told by elderly Site-Manager all the time.
Forget about those days - they are over.
What we need now are good tools to manage our work. And for time chainage schedules there were no good tools on the market yet. I even had to develope a tool in Excel with xy-Graph in the past.
I think Tilos is such a good tool. As it is developed in my home-town I have the possibility to visit the company. And I have the experience, that every call, every e-mail is answered. Problems are solved, errors corrected and suggestions included in the next version. My question about WMF-Format was answered in a peronal mail. Who ever called or e-mailed Primavera knows what this means.
Although I did not use resources and costs in Tilos yet, it is important, as clients not just pay worse, they also ask for more. - 0AFAndrew Flowerdew ·Richard,
As much as I’d like to think we never made mistakes or were in anyway inefficient in the good old days, I don’t think I’d go as far as to claim that. Hicups etc are inherent in construction projects due to thier complexity however good we think we are.
I agree that Tilos does no more than you can with a piece of paper and pen as far as determining the overall plan, a line on a screen tells you no more than a line on a piece of paper. But that line when combined with all the backgound data that can apply to it - progress, resources, outputs, quantities, costs, etc, etc - can be changed or updated somewhat quicker on screen than with a pen and the affect of the change on all that background data known at the click of a button. Speed and less prone to calculation mistakes is the advantage of computer software - at the end of the day this applies to any software, Tilos, PowerProject, P3 or whatever - I learn’t how to do CPM analysis manually before computers were around, it was invented along time before I knew it existed, but that doesn’t mean I want to go back to doing it manually and throw away P3 etc. Non of them do what couldn’t be done manually, they just do it quicker, more reliably and save alot of brain ache.
- 0PHPeter Holroyd ·there are a number of time-chainage software products around. Railway & pipeline sectors use them all the time.
It can be invaluable where multiple projects are working on the same railway for instance to give an overview of clashes between work sites
see QEI for instance - 0PJPhilip Jonker ·Hi guys,
I agree with most of you, on most points. The first point being that if you want to be a half decent planner you have to be able to plan on paper. After almost twenty years in the industry, where I planned manually, not as dedicated planners but as site managers/RE’s etc, suddenly there was software available on the market that could take the grind out of the job. Suddenly there was a market for people who could operate software. Then came the dedicated planners. They did not have the neccessary planning skills, but could operate the programs.
Projects became larger, and the detail became more intensive. You could now run huge projects and plan in detail down to the hour. The military caught on and instead of lenghty battle plans written by hand, the computor became the tool of choice, as planning software could plan by the minute or multiples thereof, and if necessary you could go to seconds. So the problem came up of how do you present all this information in a legible form? Simple, barcharts, s-curves, etc. The problem is not everybody can understand grapic representations in a two dimesional form, they want a more holistic picture. Some wanted spreadsheets with dates, others wanted other variations. Experienced individuals can read a Ghantt chart like a book, especially if the schedule is structured correctly, but you have to cater to the wider world. And, here we are talking mainly of linear projects, whether horizontally or vertically. The object is to present the project in as simple visual representation as possible, so that the safety people, IR, HR, QA, Procurement, Designers, etc, have a single picture to look at that they understand and makes sense to them. Tilos lends itself excellently to projects such as overland pipelines, motorways etc, but what about projects with non-linear activities in between, like booster pumpstations and interchanges. Here is where you have to start figuring it out for yourself.
The point is at this moment in time, I am locked into Primavera, and use Tilos as primerially a presentation tool. It works sometimes, and sometimes not. These tools, are written by programmers, without the input of planners.
This is probably not the right forum, but as a point of interest, Primavera P3 could produce s-curves with percentage progress, and the latest Primavera PM V5, cannot do this,ie % progress. It is called retrogression.
It is time for planners to stand up and demand the tools we want, and not to ripped of by software companies.
If any of you guys want to see the type of graphics tilos is capable of, I have an excellent representation, but no thanks to Tilos or primavera, we had to figure it out by ourselves.
Regards
Philip - 0PHPeter Holroyd ·But isn’t communicating the "Plan", engaging the team and gaining commitment to it what we are about - not the paper & pencils, post-it notes, spreadsheet, planning software, presentations, videos. The plan is theirs not ours - you have to "sell" it to them however you can and that’s what we get paid for.
- 0PJPhilip Jonker ·Hi Andrew,
Maybe I did not answer your question, about making the news.
The point is that if the contract your are involved in is newsworthy enough, there will be factions trying to disrupt it, some trying to stop it and others that are all for it. I am working at present on such a high profile project, that is reported on, on a daily basis in and on most of the media. There is environmental issues, personal issues, etc, all of which affects the public in general, and the most interesting part of all of this, is the predictions, by the various media presenters, of whether the project has the chance of being successful. You can study all the hype, and it ends up, that most of the media presenters prefer to go the negative route, as in their view "bad news" is "good news", ie if you rebel against something new, at least your are thinking. So the general opinion amongst journalists is shoot it down, and if it loses you are succesful. If on the other hand it is succesful, you just drop the topic and pursue another issue, so you were wrong, sorry, everybody makes mistakes.
Journalists love issues, and they are probably right in one out of ten, but this is how they make their reputation, by telling people "I told you so" , even if they have only a 10% hit rate, people have short memories, and only remeber the journalist, for being right once, even if it is once in a hundred times. What is our job? Proving them wrong yhe 99 times. - 0IAIrem Aksay ·Hello everyone
I just finished reading everything on TILOS and I saw nothing on its limitations. Not even success or failure stories. I think the topic some how went into maybe an even deeper topic. I am a young person and even I observe younger generation and sometimes think we were better(and there is not much gap btw us). But I am dead wrong... I think it is a matter of being different and not better. Software is not everything(I hope it is not because they are extremly easy to learn) but it sure gives you more time to truly analyze what you are doing. The most important thing is to take all we can from the generation before us and try to add our new tools to support them. - 0COCharleston-Joseph Orbe ·Hi Irem,
The best you can get from generation before us is manual planning. how it was done before the advent of planning software.
If you enter the electronics age of planning, it is dynamic and always young.
Take for example Primavera. How many times the software morph or upgraded that even your previous knowledge is not realiable already, meaning you have to start all over again to grasp the newer version.
Cheers,
Charlie, - 0ARAndreas Ronczka ·Hi Charlie,
interesting opinion.
Are you talking about drawing a plan or making projectmanagement? In the second case you will fail with manual drawing. You will start again and again and nobody will warn you making misstakes.
Generally, a good software guide a user through the steps and helps him while generating. I think TILOS do so!
regards
Andi - 0COCharleston-Joseph Orbe ·Andreas,
Since I belong to the young "once", im history.
Perhaps you can enlighthen us on your opinion regarding TILOS.
A good enlightenment may start with:
a.) how long you used tilos (actually, a colleague of mine want to market a new branded software name "TULO")
b.) explain further why??? A simple "I think TILOS do so" is not enough.
Please take your time. Remember, you can always come in go in PP, no hard feeling.
Cheers,
charlie
- 0ARAndreas Ronczka ·Hi Charlie,
well, I will try my very best to enlight you ;-)))
First, I work with TILOS since 1998, so that was Version 1. After several years of not good experiances the developers decide to program TILOS complete new, so Version 2 was born. I went out with this version to lots of customers from the construction side and (mostly) all of them found TILOS helpfull, but strange in handling. My collegues any I collect lots of opinions to make the software easier and more powerfull and I would say since TILOS Version 5 the developers and the strategics found the "right way".
So two things inside TILOS maks me (as consultant and user) very happy with this software:
1. If I (or any other customer) has an idea to make the software better or more clearer you could go to the developers, talk to them and a few versions later you found your idea in the software. So TILOS is a real customer tool!
2. Most software visualize your thoughts, either in kind of a barchart or as timedistance drawing. But me as user have to tell the software how I like to have my schedule. As projects gets more and more complex, cost sensitive and time critical this doesn’t really help me, I have to think about all possibilities. TILOS could assist you while your schedule. You could e.g. create links between tasks that automaticly check that no clashing (on the distance) occur . So changing the work rate of my task change the duration and TILOS make sure that my schedule still works. THATS helpfull (in my opinion).
These are only some examples, there are lots more inside the software.
Finally, in my opinion, making a schedule without TILOS is dangerous.
Could you follow my mind???
Regards
Andi - 0COCharleston-Joseph Orbe ·Hello Andi,
You scared me. I have been in planning projects for most of my time after university, and here you are telling our very own planning planet
"Finally, in my opinion, making a schedule without TILOS is dangerous."
Of course, our planning planet is unique because we can always say our opinion.
Is there a sample for tilos, let say, good for 30 activities. how to contact tilos?
Cheers,
Charlie
- 0ARAndreas Ronczka ·Whoww Charlie,
please accept my apology, I never want to scare you!
To award of misstakes let me point out:
1. We are talking about linear schedule, so a time-distance diagram is needed.
2. We are talking about doing projectmanagement rather than creating a "simple" schedule.
In this two cases I keep my opinion "...making a schedule without TILOS is dangerous...". Why?
Very easy, I don’t know any other software tool that gives me the functions I need to satisfy my requests.
If you like to know more about TILOS the easiest way is to visit there webpage www.tilos.org.
Here you also could request a demo version and ask for a web presentation.
enjoy,
Andi - 0PJPhilip Jonker ·Hi Guys and Irem,
I would would like to enter the fray here, after having been absent for a while, due to some time due to pressure.
To set the record straight, I spent some 20 years in projects, and used to do my planning myself on the drawing board, after this I spent another 16 years in planning, so I suppose I qualify as an old time planner. I have been using Tilos for about 16 months, and have found it one of the best visual tools to present the project in terms of planning, and also an excellent tool for checking the schedule (Primavera) for clashes and/or correctness. I am using Primavera PM v5, and am experiencing a lot of problems, but that is for another forum.
The way I have set it up to produce the Tilos time/distance diagram, was to run a hammock project in PM5 to minimise the number of activities in Tilos. The main reason for this is that the PM5 schedule contains some 35000 activities, a lot of which is related to design/procurement etc, ie non-construcion activities. further some of the construction activities are non-linear, ie such as shafts an buildings which happen over a limited horizontal distance, and are vertical (the projects spans a distance of 85km) so something that is even as much as 250m long shows as a vertical activities(In terms of time). The numberof activities I am running in Tilos is some 1300, and I show the baseline and forecasts, so I have some 2600 items on the diagram, excluding non-activity items and other objects. So Charlie, do not talk about 30 activities and other limitations until you have experienced it.
The main advantage is the fact that for the purposes of presentation, the diagrams produced can be understood by most people including laymen, and as such by far beats bar charts and the rest of the planning derivitives, such as histograms and s-curves etc. If you are interested, I can send you some examples in pdf format, to show you the impact of the tool, in terms of presentation.
I know you can do a time distance diagram on excel or cad, but what you want to see is what you are doing in your planning program, without the hassle.
Regards,
Philip - 0COCharleston-Joseph Orbe ·Philip,
You are always brilliant, perhaps the greatest to me with regards to planning, project management, etc. It showed in your post. I think you have 36 ++ years of experience. I’m very junior to you since I only have 23++ years of experience.
Since you address “Hi Guys” so that includes me.
I want to let you know I’m very much interested in “If you are interested, I can send you some examples in pdf format, to show you the impact of the tool, in terms of presentation.”
Please include me in your preference to send pdf format.
I really need the sample since I’m now involved with Light Rails Transit.
My e-mail address is: charlieorbe@gmail.com.
I thank you in advance for you kindness and I believe you when you said “I can send you some examples in pdf format,”.
Cheers and best regards,
Charlie
- 0PJPhilip Jonker ·Hi Guys,
Clive,
Your LOB, obviously stands for ’length of building’, which is horizontal planning turned on it’s side, ie 90 degrees. The problem is how do you reflect this on a project which is 85km (50miles) in length, when the greatest difference in height is probably less than 300m (350 yards). You are trying to show a view of the overal program, so you show these vertical structures as vertical stacked bars, if you have a solution, I would greatly appreciate it, but words like sycophantic rush definitely does not belong here. The simple way to present these vertical structures, is obviously LOB, but that means presenting each one on their own schematic diagram, which is simple, but can only be done as seperate diagram, to reflect the structure. Hope you have some better answer. By the way my project transcends some 4 cities, and is definitely not ’Greenfield’. - 0COCharleston-Joseph Orbe ·Hello Clive,
Let just be me.
This is one thing I love PP, I can be me. We can be whatever...
You dont have to react to my post, no need. I’m only a small fish in PP with 21 years ++ experience, not much compared to the big league, big guys, big time, big money, Im really nothing.
Anyway, whatever we post here will be under the watchful eyes of the moderator. The best we can do is to respect the decision of the moderators. If the post is really detrimental to the whole PP in general and specific individual PP member, there are mechanism to remove the post.
With respect to sycophancy, What I told Philip comes deep in my heart with all honesty. I always feel young, eager to learn if there is something new to me and relevanat to my work, in this case TILOS.
For the record, I prepared March Charts, Chemin de fer, Graphical Charts etc. using excel.
Cheers,
Charlie - 0PJPhilip Jonker ·Hi Guys,
I am here to share knowledge and experience, ie trying to help whomever needs it and trying to gain some experience from others who have had simular experiences. The reason I have not been such a good participant as in the past is all the bull, moderators, getting the name calling like sycopancy. Is this necessary, we are professionals andthere is no room for this.
This discussion is about Tilos and should remain as such, it is about improving the way we present our planning, and thinking lateraly, for other people to understand what we are trying to show them. It is about sharing ideas and improving the planning function.
Let’s think along these lines, and advance ourselves and our profession, instead of in-fighting.
Regards
Philip - 0PJPhilip Jonker ·Hi Andreas,
I think we have spoken on the phone, no problem sending the guys the sruff. I sent Sven a copy about two months ago, so the diagram might even be on the website. I have two different diagrams here, one of which we did for a board presentation, which has a lot of detail on. It is a good example of what can be done with Tilos in terms of presentation.
Regards,
Philip - 0AIAnoon Iimos ·Philip,
It’s very hard to read it using 14" monitor. And you need a plotter to print it on A0. Not to mention that you have to know all the symbols before you can even understand what’s drawn in there. I’m not saying that it doesn’t serve the purpose but it seems to me that it’s like a series of drawings sticked together in a scale.
It’s like a combination of autocad and excel.
Pardon for my ignorance, but if you can enlighten us a little bit, maybe we can understand. - 0PJPhilip Jonker ·Hi Anoon,
I work on a 20" monitor, and unless you study the legend and then understand it, it iis still difficult to use. However, if you know the legend and the project (distance wise) it becomes very easy to follow. I maybe need to put something together in terms of a mini description of the project to help you understand it. The printout of the whole project is normally done in A0 width, 2,1m long, so to scan around the diagram on a 14" monitor becomes very difficult.
But when working in the program, you can zoom in and click on a specific activity, and be able to see the description, start and end chainages, length, dates, and any other info you need. If you spot a problem you can then go back to the source program and correct whatever the problem is.
The vertical axis in this instance is time starting from top to bottom, and the horizontal axis is distance/chainage going from left to right. However due to the nature of the project, we have had to use split chainages. The reason for this that the alignment of the railtrack is continually being optimised, the chainages was split into 8 groups mainly around 15km each, but with one of about 3km and the longest about 17km. Furthermore there is a fork in the railwayline so two different chainages run in parrallel for about 2km. in other words, the whole system is about 85km long, so if you made tem changes in on of the 8 areas, of lets say 5 metres each, you would have to adjust all the drawings by 50m. By splitting the chainages, you only have to adjust one eight of the drawings, and the others are unaffected.
Next, was that the main area on the project is the train Depot, which is near the centre of the project, as it is the hub of all the activities, as this is where it all starts. This was allocated the 0km chainage, whichich ich midway in the 300km chainages. Then then next chainage start allocated was the 100km chainage which starts on the left of the TCD (Time chainage diagram), ie he south boundary of the project, and then the section north of that the 200km chainages, then 300km, 400km, 500km and 600km chainages respectively heading north. But, somewhere roundabout 205,040km the railtrack split into two seperate tracks, one heading east towards the international airport and the other north. This split happens just after the track exits the underground (south) section, and here the chainage changes from 200km to 700km. I hope I am explaining this clearly, as it is not that easy too explain.
This area where the two tracks run in parrallel, is one of the most critical areas in the project, as we have too cross underneath one of the busiest highways in the country, as a cut and cover. You have two railtracks running parrallel as well as all the other factors involved, such as partially undercutting a landfill site, and cropping an industrial area . This is one of the most difficult areas on the TCD to understand, as the two areas are shown seperately and it took some time figuring out how to show this. But, if you study the maps at the top of the diagram TCD, you will get the grasp of it, just remember the orientation of the maps are not always the same, but suited to the aligment. The detail of the maps show this.
So even if it looks like a mish mash of autocad and excel, which it probably is in terms, the whole thing reflects the planning in terms of the program you have developed, in this case in Primavera.
Hope this is of assistance.
Regards,
Philip - 0AIAnoon Iimos ·Hi Philip,
This is my understanding with the system as you had explained (kindly correct me if i misunderstood it):
You got x axis (horizontal) for distance scale, and y axis (vertical) for time scale. On top of this scale, you can place the mapping and the construction elements involved or the physical requirements.
But this requires tremendous details, which I believe starts from the drafting table or the drafting software for the drawings. Which means that you need to have complete drawing details prior to establishment of the chainage? Or a basic diagram / mapping will do? How can this be applicable to Engineering and Procurement?
Say, If I have a program (Level 1) considering the major milestones or contractual scope, wherein detailed design development is in progress and the inputs of approved details is on a periodic basis (i.e. monthly), Can this be inserted to the system partially to go with the incoming inputs?
I have some more questions...but this is all for now...
regards - 0AIAnoon Iimos ·sorry for the interruption, (it’s hard to work on two different things at the same time).
You mentioned that this can be interfaced with other programs (i.e. P3), isn’t it be more complicated?
I mean establishing Activities, Resources, Quantities, etc.
You gave 85 kilometer sample, (i.e. I got more that 800 kilometers) , how many people will compose the team if you need to establish the system?
regards - 0PJPhilip Jonker ·Hi Anoon,
Anything distance related, can be placed on the graphics, in this instance for the purposes of clarity, we have chosen only construction related activities, as procurement and design is not always distance related. However, it is fairly simple if your design and procurement is split into distance, and you do not have interupted chainages. The complexity of the image you want to project, is up to yourself to decide, how to interpret it, so as not to give a jumbled view. I think the final product is determined by construction, and if you see problems here, go and investigate what is the problem, whether it is design or procurement.
Regards
Philip - 0PJPhilip Jonker ·Hi Anoon,
A straight pipeline of 800km probably is less complicated than this. The number of planners you need is dependant on the number of working faces there is, and the complexity of the project, such as pump stations, distance to travel to find out what is happening etc.
Regards,
Philip - 0VLVladimir Liberzon ·Anoon,
We used Linear Diagram that is similar to Tilos View presenting Caspian Pipeline construction schedule (750 km part). It was very helpful and easy to read.
Philip,
in Spider Project you can create and use any metrics in the Linear Diagrams (example: Stage 1, Stage 2, etc.). So it is not necessary to link design with the distance. I expect that Tilos also has this option.
Vladimir