Schedule Usage
Trending
In the Open Standard
What is Trending ? How does it Work ? Incremental measurement of progress over short or long periods of Time Comparison of incremental planned progress with incremental actual progress Identifies all areas where shortfall in progress occurs Quantifies the shortfall in progress as a percentage and in
Started by admin ·
- Last updated
- Updated
- Views
- 11 views
What is Trending ? How does it Work ?
- Incremental measurement of progress over short or long periods of Time
- Comparison of incremental planned progress with incremental actual progress
- Identifies all areas where shortfall in progress occurs
- Quantifies the shortfall in progress as a percentage and in terms of manhours earned / planned and spent (actual)
- Programme Recovery Targets can be set, i.e. do more work each week than planned
- Trending relies heavily on; Comprehensive System of bottom/up information gathering both manual and computer based
- Detailed and accurate report writing, record keeping and progress input
- Interactive database computer applications