I am using powerproject. I am trying to produce a programme in working weeks ( trying to shoe the programme without holidays). Can any body help me?
Thanks

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hi Konesh,
    Display the Code Library and create a new calendar with possibly the work pattern you want to associate to this calendar.
    All the best
  2. 0
    Konesh Sridaran ·
    Thanks Alexandre

    I have done it