Non-working not shown on Summary Item Line

Tom BowlesMember for 7 years 6 months
Created
1
3
0

Hi All,

I am hoping to find a solution that displays the Non-working time shading over the task bars. I am able to format the shading over my whole programme but for some reason it 'disappears' over one particular line (68), and then reappears further down the programme. What is going on?

See image attached to better explain what I am trying to word.

Initially, my thoughts stemmed around different calendars being used, or that it was because the particular line was a 'Summary' but adjusting these seems to make no difference.

I would appreciate any help. Thank you.

Tom

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi TomWelcome to planning

    Hi Tom

    Welcome to planning plannet.

    You are showing a different calendar on the summery bar - you can only have one.

    When you add a different calendar the sytem asks if you want to switch the display - you declined.

    The tasks underneath will have the correct shading.

    Best regards

    Mike Testro