Material Allocation on Histogram Problems

Nathan WhartonMember for 13 years 1 month
Created
1
4
0

Hi All,

I am allocating material quantities to certain activities on the bar chart in order to produce a histogram.  I am putting the total material quantity total in the correct column, however in the histogram it is picking up the total quantity in each day.

For example I have an activity where a certain slab pour contains 50 tonnes of reinforcement bar.  The fixing of rebar for this activity is 6 days, so it should show about 8.3 tonnes a day, but it is just showing 50 tonnes for each day? Can anyone help as to which setting I need to click to show what I want, as I cant seem to find the right setting.

Any help would be much appreciated.

Thanks

1 reply

Oldest first
  1. 0
    Ben Taunt ·

    Hi Nathan,If I'm right and

    Hi Nathan,

    If I'm right and you are working with supported Bryne Bros licences, why not give the support helpdesk a call so you can discuss all your various questions with them?  They could post replies here but a dialogue directly with them might get you going more quickly as they can also answer your follow-up questions!

    Support's number is 01844 261609 or email support@astadev.com

    Cheers,

    Ben @ Asta