Skip to content

Histogram Problems when trying to show works done on the weekends?

Nathan WhartonMember for 13 years 1 month
Created
1
5
0

I am trying to show a histogram at the bottom of the bar chart, to show the amount of concrete that we will be pouring on site each day.  However the bar chart calendar is a mixture of 5 day, 6 day and 7 day working.  The histogram does not show the pours or works that are to be carried out on saturdays and sundays and I cant seem to make this work?  I have changed the calendar in histogram report properties to 7 day calendar and it doesnt seem to change anything.

Can anyone help?

Thanks

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi NathanYou have a resource

    Hi Nathan

    You have a resource set on tasks with different calendars.

    In the resource dialogue tick the box that says "use task calendars" and that should sort it.

    In the histogram graph dialogue you can also tick to spread over non working days.

    Hope this helps

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?