Histogram Problems when trying to show works done on the weekends?
In the Open Standard
Nathan WhartonMember for 13 years 1 month
- Created
- 1
- 5
0
I am trying to show a histogram at the bottom of the bar chart, to show the amount of concrete that we will be pouring on site each day. However the bar chart calendar is a mixture of 5 day, 6 day and 7 day working. The histogram does not show the pours or works that are to be carried out on saturdays and sundays and I cant seem to make this work? I have changed the calendar in histogram report properties to 7 day calendar and it doesnt seem to change anything.
Can anyone help?
Thanks
1 reply