Table Definition User Fields

D AsdMember for 18 years 7 months
Created
2
4
0

Hi Hopefully someone will be able to help.

 

I wish to have multiple "text only" fields in the columns. Asta bydefinition has 5 user text fields.  I need 4 or 5 more.

I have followed the asta help tool and done the following 

 1 entered the user field manager in the project tab

2  select "USER"  from the "object type" dop down.

3 Added new fields as STRING type with new names.

4 applied the setting and sved.

When i then go to the Column type as it suggests in the table nothing shows up to select.  What am I doing wrong.

 

Thankyou in advance

 

Sam

 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi DWelcome to Planning

    Hi D

    Welcome to Planning Planet

    Step 2 - Select BAR from the "Object Type" drop down - not USER.

    You can have any number of user fields in the system - just select the ones you want to display.

    Best regards

    Mike Testro

  2. 0
    D Asd ·

    Thanks Mike   I knew there

    Thanks Mike

     

    I knew there was a way.  There usually is in Asta. Cant be said of some other software...

     

     

    Sam