"ns" in predecessor / successor columns

Bo JohnsenMember for 20 years 7 months
Created
3
5
0
Hi,

Have just purchased Powerproject and is now trying to find out how it works by following some of the tutorials, help-functions and so on. I’ve also opened an existing file and as I like to see my predecessors and successors in columns by ID/line no. I’ve defined the table definitions as such.

Can anybody explain what "ns" e.g. in "ns FS 0d" means? I’ve several of those with different start dates - and they are not constrained. How does this "ns" work?

Regards,

Bo

3 replies

Oldest first
  1. 0
    Simon Martin ·
    Hi
    I may be wrong but I think it means the predecessor/successor is ’not started’.
    If you look at the properties for a particular task (right click on a bar and select ’properties’) and then look at its links, it gives you the progress for each predecessor/successor.
    Regards,
    Simon
  2. 0
    Razmik Aslanian ·

    My friendYou can find

    My friend

    You can find complete tutorial in youtube, or you can have them free from ASTA

    Regards

    Razmik Aslanian

  3. 0
    Richard Kennedy ·

    ns means the task that is

    ns means the task that is linked to/from is "not shown" in the current view, usually due to a series of tasks being collapsed from view or the task has been marked for hiding.