Skip to content

Delay Penalty for Milestones

Kannan CPMember for 18 years 4 months
Created
1
8
0

Hi,

Is there any form of Contract specifically mentioning the Delay Penalty/LDs for not meeting a milestone. In FIDIC -Red Book, in my understanding it is not clearly linked with a milestone, but for the overall works completion.

Appreciate- expert's advices.

Regards

Kannan

1 reply

Oldest first
  1. 0
    Patrick Weaver ·

    Under Common Law, failing to

    Under Common Law, failing to make progress on a project is generally not a basis for the client establishing a claim for damages. LDs are a reasonable pre-estimate of the damage suffered by the client for the late delivery of a project.  However, if the milestone is a staged handover of part of the project, then LDs can certainly be applied. 

    Example: 

    Milestone 1 - complete piling under wharf.  LDs cannot be applied, the only work following on is the contractor completing the wharf deck.

    Milestone 2 - Hand over container berth 1 for commissioning (project involves several berths). LDs can apply the handover allows the client to start work towards earning revenue. 

    Civil Law is a bit different, it allows the partie to a contract to pre-set damages for failing to achieve a contractual objective.

    For more on LDs see: https://mosaicprojects.com.au/PMKI-ITC-020.php#Process1

     

       

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?