Loss of Efficiency Claim

Shahzad MunawarMember for 23 years 3 months
Created
2
1
0
Can we include and claim loss of efficiency due to uneconomical working in our prolongation claim because this efficiency of labour, equipment etc is also effected due to delay in completion of works ?

2 replies

Oldest first
  1. 0
    Scott E ·
    You may be talking about a disruption claim. That is, due to a great number of variations to a contract a loss of working efficiency has occured due to the disruption in works and inability to plan the job.

    Due to this disruption costs cannot be assoicated with individual contract variations. The result is usually submission of a global type claim.

    Global claims are becoming more accepted than they once were.
  2. 0
    Forum Guest ·
    See excellent article at maple-consult.com.